GENOSAFE

Lieu du projet : Evry
Période : 2019-2021
Donneur d'ordre : Genosafe
Mission : Project management with OPC
Montant des travaux : Between 5 and 10 M€.

Within the framework of this project, ATRIX teams have provided the fitting out of 2 laboratory floors (CRO Laboratory - Class C - BSL2 and BSL3) for Genosafe.
The phases concerned are : ESQ - APS - APD - PRO - ACT - EXE - DET - OPC.

Surface area 1200 m²
5-storey building including 3 floors of offices and 2 technical floors
The laboratories allow the following activities to be housed:
A biomolecular laboratory area BSL2
A BSL2 and BSL3 cell culture laboratory area
A shop
A laundry
Archiving and cold storage areas.

Lots managed by the ATRIX teams

  • Finishing work
  • Laboratory furniture
  • HVAC
  • High/low current electricity
  • Fluids
  • Thermal fluids
IMAGES DU PROJET :